The insulation passed inspection today, so they can start sheet rock tomorrow. Today they added something to attach the ceiling sheet rock to (rather than directly to the rafters):

p9100001.jpg

And they also nailed down the plywood subfloor more permanently (except for a couple of pieces to allow the heating installers access:

p9100002.jpg

They also primed some mysterious pieces of trim; not sure what it’s for yet:

p9100003.jpg

And they did…stuff…along the bottoms of the wall. Shiny stuff:

p9100004.jpg

And the boiler looks much closer to ready to go, with pipes and vents and all sorts of neat things:

p9100005.jpg

And again, hooray for our contractor, who found someone to take away the 200+ gallons of heating oil left in our tank. The company we bought from showed no interest in taking it back, even without crediting us any money.

We apparently have to make decisions about the built-ins within a day or two, so I assume that’s coming soon, which makes sense. Vroom vroom!